Dyke Waste Water
Treatment Works

Duration
34 weeks

Client
Scottish Water

Demolition of existing Primary Settlement Tank & Tool Shed. Replacement of existing boundary fence. Construction of an Inlet Screen Chamber with Storm By-pass, installation of Packaged Bioreactor Sewage Treatment Unit and construction of a 1.2m diameter Outlet Pumping Station and Valve Chamber with all associated pipework.

Construction of a purpose built Control & Mess Building, laying of site hardstanding and modifications to existing.

 

Tulloch Civil Projects